Tuesday, May 7th, 2013, Next Level Almost All Dug Out

Posted on May 7, 2013 by gojajah
Reply
May 7, More Rapid soil removal

May 7, More Rapid soil removal

The next layer is almost all dug out.

Posted in Uncategorized | Leave a reply

Monday, May 6th, 2013…The digging Continues

Posted on May 6, 2013 by gojajah
Reply

Digging continues today with just a few tracks removing soil.

More Digging

More Digging

Posted in Uncategorized | Leave a reply

Friday, May 3rd, 2013. Looks Like One More Level Down

Posted on May 3, 2013 by gojajah
Reply

May 5, One more level to go

May 5, One more level to go

Today it looks like there is stll one mre level down to go.
Trucks are taking more soil out on the new ramp.

Posted in Uncategorized | Leave a reply

Thursday, May 2nd…The Hole is Accessible Again

Posted on May 2, 2013 by gojajah
Reply
The Hole is Accessable Again

The Hole is accessible Again

Posted in Uncategorized | Leave a reply

Tuesday, April 30th, Reinforcement of all walls is almost complete

Posted on April 30, 2013 by gojajah
Reply

Here at the parking lot by the Jajah Mountain View there is a lull in the earth moving activity.

All of the soil is in the center and the walls are being reinforced.

The ramp dirt sits in the center of the hole.

The ramp dirt sits in the center of the hole.

 

Across the road soil is being added to the site.

Adding Soil across the road

Adding Soil across the road

 

Posted in Uncategorized | Leave a reply

Thursday, April 25, New Round of Activity

Posted on April 25, 2013 by gojajah
Reply

Today it looks like they are cinally going to move the earthen ramp and finish reinforcing the walls.

April 12, Getting Ready to Move Ramp

April 12, Getting Ready to Move Ramp

 

Meanwhile across the road a lit of grading is being done.

April 25, Across the road grading is underway.

April 25, Across the road grading is underway.

 

Posted in Uncategorized | Leave a reply

Wednesday, April 24, Another Quite Day

Posted on April 24, 2013 by gojajah
Reply

Very little activity today.
But there are a lot of People.

April 24, People Assembling

April 24, People Assembling

Posted in Uncategorized | Leave a reply

Monday, April 22, 2013 The day starts quite and tidy

Posted on April 22, 2013 by gojajah
Reply

Very quite in the hole today.

April 22, Quite Start

Neat and quite.

April 22, Neat and Quite

April 22, Neat and Quite

Posted in Uncategorized | Leave a reply

Friday, April 19th. Very substantial Activity.

Posted on April 19, 2013 by gojajah
Reply
April 19 Soil Removal

April 19 Soil Removal

Friday, end of week. It is hard to believe that there is any more soil left in the parking lot hole but the work continues.

A side view.

April 19 Side View of activity

April 19 Side View of activity

The reinforcing rods that are driven into the side walls.

Wall reinforcing rods

Wall reinforcing rods

Posted in Uncategorized | Leave a reply

Thursday 18th of April, 2013 Are we there yet?

Posted on April 18, 2013 by gojajah
Reply

The hole in the parking lot at the Jajah office in Mountain View is planned to be three stories deep.

It seems like it must be close.

April 18 The Trucks Gather

April 18 The Trucks Gather

The Side wall reinforcing is progressing quickly.

April 18 Truck Circle

April 18 Truck Circle

 

Posted in Uncategorized | Leave a reply

Post navigation

← Older posts

Topics

Follow us on facebook

jajah on facebook
Theme: Twenty Eleven | Blog at WordPress.com.
Follow

Get every new post delivered to your Inbox.

Powered by WordPress.com